A crew opens a wall and finds damaged framing. The owner tells the contractor to replace it so the job can stay on schedule. The contractor does the work and includes it in the next payment application. The owner points to the contract’s signed change-order requirement and refuses to pay.
Can the contractor still get paid? Possibly. On a private construction project in North Carolina, a later agreement or the parties’ conduct can sometimes modify or waive a signed change-order requirement. The contractor still needs evidence that the work fell outside the original scope, that the person who approved it had authority, that the contractor was entitled to extra payment, and that the amount claimed is supported.
Was the work actually extra?
Start with the contract, drawings, specifications, and any proposal exclusions that became part of the agreement. In the framing example, the answer may turn on whether the original price included repairing concealed damage.
Read the change-order and notice provisions together. Who can approve extra work? Who must receive notice, in what form, and by when? Can the owner direct the crew to proceed while pricing is unresolved? Check separate notice deadlines and cost-record requirements even if the parties appear to have set aside the signature requirement.
What did “go ahead” mean?
In Garrison Grading, the parties orally agreed on unit prices for extra excavation, and the other party’s engineer requested and supervised the work. In Inland Construction, the owner initiated additional HVAC work and its architect, whose authority to act for the owner was undisputed, directed the contractor to proceed. In both cases the contractor recovered despite the missing written approval.
In Cape Fear Electric, project engineers insisted that the contractor install more expensive conduit. Even assuming it was extra, the court found no evidence that the owner authorized the engineers to commit it to a higher price or that the owner waived the change-order requirement. The contractor’s claim against the owner failed.
Clarify what “go ahead” means while everyone is still on the job. Did someone with authority approve the quoted price, authorize time-and-materials billing, or direct the crew to proceed while leaving payment unresolved? Record who gave the instruction, when, and what work it covered.
What if no price was agreed?
An instruction to proceed can help show that the work was authorized. The contractor still needs a basis for charging extra and evidence to support the amount. Start with the contract. It may specify unit rates or a method for calculating labor and material costs. In Garrison Grading, the parties had agreed on unit prices, and the contractor’s daily load counts helped establish the quantity of excavation.
In some cases, a contractor may be able to recover the reasonable value of the extra work, including where the parties abandoned the written change-order procedure. When the contract governs payment for the work, its terms generally control. If a reasonable-value claim is available, an invoice alone may be insufficient. Time records, supplier invoices, and evidence of customary rates can help support the amount claimed.
What should each side do when the scope changes?
If you’re the contractor, follow the contract’s notice procedure and send the request to the designated person. Identify the extra work, explain why you believe it falls outside the original scope, and provide a price or explain how you’ll track the cost. Flag any schedule impact. If the contract requires you to proceed before the dispute is resolved, follow its procedures for preserving your claim.
If you’re the owner, respond promptly. If you believe the work is already included, point to the provision or drawing you’re relying on. If the crew needs to proceed while scope or price is disputed, put the direction in writing and identify what remains open. Make sure your project team knows who can approve changes.
What if the work is already done?
Build a timeline from the first request through the first invoice. Gather the contract, drawings, emails and texts, daily reports, photos, time records, invoices, and prior change orders. Pin down who requested the work, when the contractor identified it as extra, what was said about payment, and when either side objected.
Ask what the project records would tell someone who wasn’t there. That’s a good starting point for deciding whether to pay, dispute, or negotiate the charge.
This article provides general information about private construction projects in North Carolina.